garvasban
bann01

Art: 400; 401; 402; 403

bann01
click to enlarge
bann01
click to enlarge
bann01
click to enlarge click to enlarge
bann01
click to enlarge click to enlarge click to enlarge
bann01
  1. COAT THE INSIDE OF THE MOLD WITH MOTOR OIL
  2. DO NOT USE UNREFINED OIL OR EDIBLE OIL
  3. FIX CONICAL FORMER TO BASE-BOARD AND COAT WITH MOTOR OIL (Pict. 1)
  4. JOIN THE TWO HALVES OF THE MOLD USING SCREWS
  5. PLACE OVER CONICAL FORMER AND HOLD TIGHT ONTO BASE-BOARD USING STRONG ROPE (Pict. 1)
  6. MIX CONCRETE (0-1 mm GRANULATION) IN PROPORTION 1:3
  7. ROTATE THE MOLD TO ACHIEVE EVEN SETTING WHILE POURING IN THE CONCRETE
  8. TOWARDS THE END OF SETTING PERIOD, INSERT TWO 6mm RODS AS SHOWN
  9. ALLOW THE WASE TO DRY FRO 24 HOURS
  10. LATER, DRILL A HOLE FOR DRAINAGE
  11. THE VASES ART. 402 IS COMPLETED BY JOINING THE TWO PARTS USING CONSTRUCTION GLUE
bann01
Hand-hold Back Facade stone